6.6 Assessment and acceptance

    6.6.1 Collection and comprehensive analysis shall be conducted forthe inspection and testing results of seepage control and drainageeffects, optimization and modification of design and construction ofseepage control works, and updating of engineering geol...[继续阅读]

水电工程施工地质规程

7.1 General requirements

    7.1.1 The geological work for slope works lasts throughout theslope excavation and after formation of final sections.7.1.2 The geological work for slope works shall include thefollowings.(1) Routine geological inspection and observation, and collection of...[继续阅读]

水电工程施工地质规程

7.2 Geological inspection and observation

    7.2.1 The geological inspection for rock slopes shall include thefollowings.(1) Excavation progress, procedures, methods, techniques andinfluences of construction quality on slope stability.(2) Characteristics of discontinuity combination (particularly th...[继续阅读]

水电工程施工地质规程

7.3 Sampling and testing

    7.3.1 The following rock/soil samples should be collected duringthe excavation.(1) Representative rock/soil samples, particularly the special rock/soillike soluble rock/soil, swelling rock/soil, soft soil and collapsible soil.(2) Substances of weak interb...[继续阅读]

水电工程施工地质规程

7.4 Geological prediction

    7.4.1 Analysis and judgment shall be made on causes, charactersand potential hazards of the following phenomena, and geologicalprediction shall be made in time.(1) Continuous small-scale collapse and dislocation, rock falling,bending, overturning and buck...[继续阅读]

水电工程施工地质规程

7.5 Geological mapping and logging

    7.5.1 The final slope faces shall be mapped and logged. Geologicallogging shall be conducted for slopes greatly affecting the safety andoperation of main structures; geological mapping may be conductedfor slopes of permanent structures like embankment dam...[继续阅读]

水电工程施工地质规程

7.6 Assessment and acceptance

    7.6.1 Various investigation data and geological results shall becomprehensively utilized to update the slope engineering geologicalassessment.7.6.2 Engineering geological assessment of the whole or partialslope should include the followings.(1) Slope geom...[继续阅读]

水电工程施工地质规程

8.1 General requirements

    8.1.1 The geological work for natural construction materials shallcover the mining and utilization of earth materials, natural sand andgravel, rock materials as well as materials excavated from projectsite.8.1.2 The geological work for natural constructio...[继续阅读]

水电工程施工地质规程

8.2 Geological inspection and observation

    8.2.1 The geological inspection for borrow areas should include thefollowings.(1) Changes in thickness of stripping layers and available layers.(2) Distribution of unavailable layers.(3) Whether the mining methods affect the quality and reserve ofearth ma...[继续阅读]

水电工程施工地质规程

8.3 Sampling and testing

    8.3.1 Sampling and testing shall be conducted in case of utilizingadditional excavated materials from project site.8.3.2 The rock/soil mass and discontinuities affecting the stabilityof slopes in borrow areas and quarries shall be sampled for testing.8.3....[继续阅读]

水电工程施工地质规程
科普知识
心理健康 优生优育 休闲旅游 健身美容 饮食健康 人与自然 地球家园 海洋技术 科海拾贝 科学之迷 科技前沿 科技史话 科幻未来 神话传说 童话故事 致富指南 农用物资 生物技术 畜牧兽医 园林花卉 特产养殖 营养早餐 减肥晚餐 晚餐食谱 营养晚餐 减肥中餐 中餐文化 中餐菜谱 中餐营养 健康早餐 减肥早餐 早餐食谱 晚餐禁忌 宝石鉴定 安全生产 安装钳工 钣金技术 宝石观察 焙烤工业 变性淀粉 插花技能 车工技术 道路工程 低压电器 电气工程 电气设备 电网工程 电源技术 电站工程 淀粉科学 调味配方 发电节能 防水材料 飞机飞行 服装生产 钢铁材料 工程建设 工业工程 公路工程 管道工程 罐头工业 国际组织 国家电网 华北电网 火电工程 货运物流 机床设计 机电工程 机修钳工 基本资料 家用电器 建设工程 节约用电 金银技术 金属材料 连续铸钢 轮机工程 奶牛养殖 农村电工 配电技术 皮革工业 啤酒工业 苹果产业 钳工简明 青工车工 青年审美 肉类工业 入侵检测 食品科学 世界修船 兽医兽药 水下工程 税收制度 通信设备 统计公文 土木工程 维修电工 味精工业 文物鉴赏 物业电工 铣工计算 线损管理 鞋楦设计 烟草工业 盐业产品 冶金产品 液压技术 印刷科技 用电管理 油墨技术 轧钢技术 粘接技术 照明设计 制浆造纸 土元养殖 兔场疾病 外国美术